Meeting to be held 25 March 2026
(Appendices 1 - 3 refer)
Contact for further information:
Steven Brown - Director of Corporate Services – Telephone Number 01772 826804
Executive SummaryThe report sets out the budget position to the end of January in respect of the 2025/26 revenue and capital budgets. RecommendationThe Committee is asked to: · Note and endorse the financial position. · Approve slippage in the capital programme of £0.019 million to 2026/27
|
Lancashire Fire and Rescue Service’s 2025/26 revenue budget has been set at £77.511 million. The budget profiled to the end of January 2026 is £61.604 million and expenditure for the same period is £61.403 million which is essentially breaking even.
The budget included £0.5 million of savings to be delivered through effective deployment of resources and effective management of overtime, management information shows that overtime has been avoided and therefore we are forecasting that these savings will be met.
Overall, a small underspend is forecast of £0.184 million, which is just 0.2% of our net budget. The year-to-date and forecast positions within all departmental budgets are set out in Appendix 1, with the major variances of note shown separately in table 1.
Area |
Year to Date |
Forecast |
Reason |
|
Service Delivery - Pay |
£0.274 million |
£0.359 million |
The variance is largely due to two factors; the pay award of 3.2% from July 2025 is 0.2% above our budgeted assumptions, and higher than budgeted activity levels for on call staff. |
|
Prevention and Protection - Pay |
(£0.316 million) |
(£0.361 million) |
As previously reported to the Committee vacant posts have remained throughout the year. Successful recruitment campaigns have been offset by leavers. Challenges continue to persist in recruitment and retention due to competition from the private sector. |
|
Non devolved financial management (DFM) - Insurance Liability |
£0.184 million |
£0.184 million |
An Employers’ Liability claim relating to a historical case continues to be managed by our insurers. During the year, costs associated with this claim have progressed to the point where the Service has become liable for the insurance excess. This has resulted in payments being made in‑year in accordance with the policy terms. There will be no further costs associated with this claim for Lancashire Fire and Rescue Service (LFRS). |
Table 1 – Major variances of note
Although not reflected in the 2026/27 budget set in February, the escalating conflict in the Middle East presents a growing financial risk. Geopolitical instability has already contributed to higher‑than‑assumed inflation, particularly in energy markets, with utility costs now tracking above 6% compared to the 2% inflation assumption underpinning the budget. This sustained volatility may increase pressures on fuel, utilities, supply‑chain‑dependent non‑pay budgets, and capital project costs throughout the year. Given the continued uncertainty in global markets, these factors have the potential to create additional in‑year pressures and will require close monitoring and potential adjustment within future financial planning cycles.
The 2026/27 budget includes a 4% increase for both green and grey book pay awards. National negotiations for the 2026 pay awards are underway. For Green Book staff (effective April 2026), the recognised National Joint Council (NJC) unions have submitted a formal pay claim seeking a minimum increase of £3,000 or 10%, alongside a £15 minimum hourly rate and improvements to working time and leave. Employers have not yet tabled a counter‑offer, with a response expected later in March. For Grey Book staff (effective July 2026), the Fire Brigades Union (FBU) has initiated discussions and is pressing for a substantial above‑inflation increase, although no specific figures or employer proposals have yet been published. We will continue to monitor national negotiations and update Members once formal offers are issued.
To deliver the £0.5 million savings required for 2025/26 the Dynamic Resource Management (DRM) policy came into effect on 1 July which provides steps which can be taken prior to using overtime to fill shortfalls, including using the fifth crew member from the Urban Search and Rescue (USAR) stations and redistributing the crew from second pumps at two pump wholetime stations where there is adequate fire cover in the area. The saving target has been delivered.
The Productivity and Efficiency Plan for 2025/26 includes £0.572 million of savings to be delivered in 2025/26; the delivery of £0.5 million has been explained above. The balance of £0.072 million is a balance of some smaller initiatives such as procurement savings, this will be reported through our update of progress against the plan later in the year.
The General Reserve exists to cover unforeseen risks and expenditure that may be incurred outside of planned budgets. In February 2026 the Authority approved the minimum level of General Reserve as advised by the Treasurer at £4 million.
The year end forecasted general fund position is summarised below which is above the minimum level of General Reserve approved by the Authority:
|
|
£' million |
|
Opening balance of LFRS general fund |
(5.556) |
|
Forecast revenue underspend |
(0.184) |
|
Forecast closing balance of general fund |
(£5.740) |
Table 2 - year end forecasted general fund position
The revised Capital Programme for 2025/26 was approved by the Authority at £7.190 million, to date £4.371 million has been spent to the end of January. A summary of the programme is set out in the table below and in more detail in Appendix 2.
Area |
Budgeted Items |
Budget |
Year to Date |
|
Operational Vehicles Budget
|
The budget includes the purchase of four Type B pumping appliance Chassis. |
£0.719 million |
£0.149 million |
|
Other vehicles Budget |
This budget allows for the replacement of various operational support vehicles including several cars, vans and a welfare unit. |
£1.120 million |
£0.706 million |
|
Operational Equipment Budget
|
This budget allows for operational equipment purchases including Breathing Apparatus, CCTV cameras for appliances, ballistic vests and helmets, flow meters and hose reel, cutting and extrication equipment. |
£1.061 million |
£0.506 million |
|
Building Modifications Budget
|
This budget includes the continued programme of Drill Tower Replacements, upgrades to Preston and Blackpool stations. |
£3.173 million |
£2.460 million |
|
IT systems Budget |
This budget includes various projects including upgraded Firewalls, network upgrades, Retained Duty System Alerts, North West Fire Control (NWFC) Dispatch System and replacement of each protection, pooled Personal Protective Equipment (PPE) and stock management systems. |
£1.117 million |
£0.549 million |
|
- |
- |
£7.190 million |
£4.371 million |
Table 3 - revised capital programme
In addition, further slippage of £0.019 million relating to ICT is requested to be transferred to the 2026/27 capital programme.
There are several potential scenarios that have not been reflected in this monitoring report that, if they materialise, may give rise to an increase in revenue and capital expenditure. To provide some information about potential significant financial risks these have been quantified to provide an estimated worst case scenario, these are set out in Appendix 3. Taking all these risks overall and adjusted for the remainder of the year, a potential worst-case scenario would impact the Revenue Budget and Capital Budget accordingly:
|
£ million |
Worst Case |
|
Revenue Budget - unbudgeted costs |
1.1 |
|
Capital Budget – Additional Expenditure |
0.2 |
Table 4 – potential worst-case scenario revenue budget and capital budget
The potential worst-case scenario could be funded from available budgets but would reduce the general fund balance to below the minimum acceptable level agreed by the CFA.
As outlined in the report.
None.
None.
None.
None.
None.
Paper:
Date:
Contact:
Reason for inclusion in Part 2 if appropriate: N/a
Directorate Finance Management
|
Revised Annual Budget |
Year to Date Budget |
Year to Date Total * |
Year to Date Variance |
Year to Date Variance Pay |
Year to Date Variance Non-Pay |
Forecast Outturn Variance Overspend (Underspend) |
Forecast Outturn Variance Pay |
Forecast Outturn Variance Non-Pay |
Service Delivery |
- |
- |
- |
- |
- |
- |
- |
- |
- |
|
Service Delivery |
44.487 |
37.352 |
37.684 |
0.331 |
0.274 |
0.058 |
0.397 |
0.359 |
0.038 |
|
Prevention and Protection |
3.914 |
3.271 |
2.955 |
(0.316) |
(0.316) |
0.000 |
(0.350) |
(0.361) |
0.011 |
|
Control |
2.237 |
2.237 |
2.201 |
(0.036) |
0.000 |
(0.036) |
(0.036) |
0.000 |
(0.036) |
|
Youth Engagement (including Princes Trust) |
0.022 |
(0.041) |
(0.042) |
(0.001) |
0.008 |
(0.009) |
0.002 |
0.010 |
(0.008) |
|
Special Projects (ISAR) |
0.002 |
0.002 |
(0.004) |
(0.006) |
0.000 |
(0.006) |
(0.009) |
0.000 |
(0.009) |
Strategy and Planning |
- |
- |
- |
- |
- |
- |
- |
- |
- |
|
Service Improvement |
2.607 |
2.165 |
2.149 |
(0.016) |
0.013 |
(0.030) |
(0.013) |
0.015 |
(0.028) |
|
Leadership and Development Centre |
4.638 |
3.794 |
3.664 |
(0.130) |
(0.090) |
(0.040) |
(0.128) |
(0.095) |
(0.033) |
|
Fleet and Technical Services |
3.582 |
2.912 |
2.926 |
0.014 |
(0.000) |
0.014 |
0.024 |
0.000 |
0.024 |
|
Digital Data and Technology (DDAT) |
4.576 |
3.416 |
3.369 |
(0.047) |
(0.003) |
(0.045) |
(0.068) |
(0.000) |
(0.067) |
People and Development |
- |
- |
- |
- |
- |
- |
- |
- |
- |
|
Human Resources |
1.007 |
0.841 |
0.839 |
(0.001) |
0.009 |
(0.011) |
0.025 |
0.031 |
(0.006) |
|
Occupational Health Unit |
0.372 |
0.310 |
0.220 |
(0.090) |
(0.023) |
(0.067) |
(0.072) |
(0.038) |
(0.034) |
|
Corporate Communications |
0.479 |
0.399 |
0.357 |
(0.042) |
(0.023) |
(0.019) |
(0.027) |
(0.026) |
(0.000) |
|
Safety Health and Environment |
0.335 |
0.281 |
0.288 |
0.007 |
0.017 |
(0.010) |
0.050 |
0.018 |
0.032 |
Corporate Services |
- |
- |
- |
- |
- |
- |
- |
- |
- |
|
Executive Board |
1.197 |
1.009 |
1.046 |
0.037 |
0.038 |
(0.001) |
0.054 |
0.059 |
(0.005) |
|
Central Admin Office |
0.716 |
0.596 |
0.492 |
(0.104) |
(0.086) |
(0.018) |
(0.107) |
(0.101) |
(0.006) |
|
Finance and Procurement |
1.352 |
1.037 |
1.017 |
(0.020) |
(0.017) |
(0.003) |
(0.015) |
(0.019) |
0.004 |
|
Property |
3.414 |
2.412 |
2.424 |
0.012 |
(0.075) |
0.087 |
(0.010) |
(0.087) |
0.077 |
Subtotal |
74.939 |
61.993 |
61.585 |
(0.408) |
(0.273) |
(0.135) |
(0.283) |
(0.236) |
(0.047) |
Non Directorate Finance |
- |
- |
- |
- |
- |
- |
- |
- |
- |
|
Pensions Expenditure |
1.552 |
1.210 |
1.204 |
(0.006) |
- |
(0.006) |
- |
- |
- |
|
Other Non-DFM Expenditure |
1.021 |
(1.599) |
(1.386) |
0.213 |
(0.016) |
0.229 |
0.099 |
(0.005) |
0.105 |
Subtotal |
2.572 |
(0.389) |
(0.182) |
0.207 |
(0.016) |
0.223 |
0.099 |
(0.005) |
0.105 |
Grand Total |
77.511 |
61.604 |
61.403 |
(0.201) |
(0.289) |
0.088 |
(0.184) |
(0.241) |
0.057 |
Table 5 - Directorate Finance Management Budget Monitoring Statement
Capital Budget 2025/26 £ million |
Revised Programme |
Actual as at January 2026 |
Slippage to be approved at March 2026 Resources |
Over or (Under) Spend as at January 2026 |
Projected Year End Outturn |
Projected Year End Over or (Under) Spend |
Vehicles |
- |
- |
- |
- |
- |
- |
|
Operational Vehicles |
0.719 |
0.149 |
0.000 |
(0.570) |
0.719 |
0.000 |
|
Support Vehicles |
1.120 |
0.706 |
0.000 |
(0.414) |
1.086 |
(0.034) |
Subtotal |
1.839 |
0.855 |
0.000 |
(0.984) |
1.805 |
(0.034) |
Operational Equipment |
- |
- |
- |
- |
- |
- |
|
Operational Equipment |
1.061 |
0.506 |
0.000 |
(0.555) |
0.883 |
(0.178) |
Subtotal |
1.061 |
0.506 |
0.000 |
(0.555) |
0.883 |
(0.178) |
Buildings Modifications |
- |
- |
- |
- |
- |
- |
|
Update Preston Facilities |
0.433 |
0.139 |
0.000 |
(0.294) |
0.433 |
0.000 |
|
Development and Land Acquisition |
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
Blackpool Dormitory |
0.498 |
0.516 |
0.000 |
0.018 |
0.516 |
0.018 |
|
Drill tower replacements |
1.381 |
1.005 |
0.000 |
(0.376) |
1.381 |
0.000 |
|
Wylfa Prop |
0.175 |
0.153 |
0.000 |
(0.022) |
0.192 |
0.017 |
|
STC Props |
|
0.111 |
0.000 |
0.111 |
0.135 |
0.135 |
|
Estate Improvement Provision |
0.686 |
0.537 |
0.000 |
(0.149) |
0.653 |
(0.033) |
Subtotal |
3.173 |
2.460 |
0.000 |
(0.713) |
3.310 |
0.137 |
ICT |
- |
- |
- |
- |
- |
- |
|
IT Systems |
1.117 |
0.549 |
0.019 |
(0.549) |
1.046 |
(0.052) |
Subtotal |
1.117 |
0.549 |
0.019 |
(0.549) |
1.046 |
(0.052) |
Grand Total |
7.190 |
4.371 |
0.019 |
(2.800) |
7.044 |
(0.127) |
Funding |
- |
- |
- |
- |
- |
- |
|
Revenue Contributions |
2.500 |
2.501 |
0.019 |
0.020 |
2.354 |
(0.127) |
|
Capital Reserves |
4.690 |
1.870 |
0.000 |
(2.820) |
4.690 |
0.000 |
Total Capital Funding |
7.190 |
4.371 |
0.019 |
(2.800) |
7.044 |
(0.127) |
Table 6 – Capital Budget 2025/26
Appendix 3
Potential significant risks have been quantified to provide an estimated best case and worst-case scenario for each risk.
|
|
Revenue or Capital |
Worst Case (Full Year)£ million |
|
Industrial Action (Risk 1a) – Costs based on reported figures from other fire authorities adjusted for inflation and size of authority. |
Revenue |
2.5 |
|
Pandemic (Risk 1d) – Based on direct costs of COVID19, this was funded but this scenario assumes no funding provided. |
Revenue |
1.3 |
|
Overspending and future financial pressures on the medium term financial strategy (MTFS) due to increase in costs of goods and services and pay (Risk 2b) – based on highest one year consumer price index (CPI) increase experienced of 13.5% |
Revenue |
2.0 |
|
As above |
Capital |
1.3 |
|
Loss of Utilities (Risk 3) and ICT (Risk 4) – Includes additional repair costs, overtime, hire costs etc |
Revenue |
0.2 |
|
Operational Event (Risk 11) – large scale incidents and events can be significant however there are funding mechanisms such as Bellwin in place. This cost assumes a prolonged period of overtime that would not be met from national funding schemes. |
Revenue |
0.5 |
Revenue Total |
- |
6.5 (residual risk in 2026/27 1.1) |
Capital Total |
- |
1.3 (residual risk in 2026/27 0.2) |
Table 7 – Worst case scenario of potential significant risks